Holly Ridge's wastewater plant is a lagoon at 286 North Jenkins Street. Most people who drive US 17 through town have never seen it. Treated water leaves the lagoon through 17,900 feet of force main and goes to a spray irrigation site on Dolph Everett Road, where ten spray fields cover 93.42 acres. For anyone shopping for a new home in Holly Ridge, its limits will matter more over the next three years than any builder's brochure.
The Onslow Water and Sewer Authority runs the plant, and its 2025 wastewater annual report says the system averaged 0.250 million gallons a day across calendar year 2025. Its permit allows 0.240. That put it at 104% of permitted capacity for the year. More sewer capacity is scheduled to arrive in late 2028 or early 2029. In the meantime, at least one new Holly Ridge subdivision is moving ahead without public sewer, and its plat shows what that does to the homes.
The 2025 numbers from the plant
ONWASA lists the lagoon at 0.260 million gallons a day and the Dolph Everett Road spray site at 0.240, and its report uses the spray site's figure as the plant's actual capacity. In 2025 the plant handled 91.7 million gallons, 18.5% more than in 2024, and its busiest day of the year was June 16, at 0.395 million gallons. The report says yearly totals can swing a lot depending on how much flow gets diverted between Holly Ridge and the Summerhouse plant. So the more useful figure is the 104% average for the year.
When more capacity arrives, step by step
ONWASA isn't expanding the Jenkins Street plant. It plans to shut it down. Holly Ridge's wastewater will instead be piped to Summerhouse on Everett Bay, which has its own treatment plant, and from there to the Southeast Regional plant in Sneads Ferry, formerly called North Topsail.
| Step | Status in ONWASA's records |
|---|---|
| Force main and pump station, Holly Ridge plant to Summerhouse | Under construction during 2025 |
| Summerhouse Phase 1 interim upgrades to take Holly Ridge flow | Under construction during 2025; completion expected in 2026 |
| Pipeline from Summerhouse to the Southeast Regional plant | In design during 2025 |
| Southeast Regional plant expansion to 3.5 million gallons a day | Expected late 2028 to early 2029 |
ONWASA signed a progressive design-build contract for the Sneads Ferry expansion. When finished, that plant will take flow from the Holly Ridge plant, Summerhouse, the Camp Davis Industrial Park, and "anticipated residential and commercial development." In 2024, ONWASA's annual report gave 2028 as the completion year. The 2025 report moved that to late 2028 or early 2029.
At its May 15, 2025 meeting, the ONWASA board heard that Summerhouse Phase 1 was "finishing up" and that Phase 2 would follow. The same meeting covered a second force main to link the Camp Davis and Holly Ridge service areas to the Southeast plant along US 17 and NC 172. All of these projects are steps toward the expanded plant, which ONWASA expects in late 2028 or early 2029.
Tar Landing shows what gets built before then
Tar Landing, off Tar Landing Road, is a project that decided not to wait. On December 10, 2024, Holly Ridge's Town Council approved a concept plan for a planned unit development of about 98 acres. It allows roughly 225 single-family homes, townhomes and duplexes, about 2.3 units an acre, with about 29 acres of open space.
Sewer was still unavailable when Phase 1 reached the town's Planning Board on October 20, 2026. The town's staff report quotes an ONWASA email saying sewer is not expected until 2028 "as long as everything goes as planned." The developers chose not to wait and proposed septic systems for the lots. ONWASA will still supply water. The owner is Tar Landing Group LLC, the developers are Newton D. Sasser and Wally Diehl, and McKim & Creed is the engineer.
The lot sizes show what septic does to a subdivision. The approved concept allowed lots as small as 5,000 square feet. Phase 1 has 36 lots on 19.85 acres, and the average lot is 0.32 acres, or 13,939 square feet. The smallest is 0.17 acres. The plat calls for private and community septic systems and ONWASA water, with 24-foot paved streets, curb and gutter, and a five-foot sidewalk on one side of the road. Town staff wrote that switching to septic makes the project less dense than approved.
So the first phase of Tar Landing will look more like a rural subdivision than the townhome-and-duplex mix in its approved plan. Its homes will sit on lots close to a third of an acre, built at the pace of a 36-lot first phase.
What's for sale now in Holly Ridge
The communities selling now sit at very different price points. Dream Finders Homes lists The Townhomes at Gateway Commons at 221 Senna Drive from $236,990, with floor plans of 1,373 to 1,422 square feet. In mid-November 2026 the builder showed two move-in-ready homes, both 1,422 square feet and both priced at $236,990.
At the other end, 70 West Builders listed a quick move-in home at Summerhouse on Everett Bay in mid-November 2026: four bedrooms, 2,929 square feet, $650,000. Summerhouse has its own ONWASA reclamation plant, separate from the Jenkins Street lagoon. Atlantic Construction lists Tides End as its Holly Ridge community, with no prices posted on its community page. D.R. Horton's Holly Ridge page showed no homes for sale within three miles in mid-November.
That leaves two posted new-home prices about $413,000 apart: roughly $237,000 for a 1,422-square-foot townhome at Gateway Commons and $650,000 for a 2,929-square-foot home at Summerhouse. Tar Landing's first phase, on lots averaging 0.32 acres, will be the next new subdivision to compare against them.
The larger proposals on the calendar
Larger proposals are on the town's calendar too. In February the Wilmington StarNews reported that a proposed annexation that would double Holly Ridge's size had moved forward. Its headline said the annexation could bring thousands of homes to the Pender-Onslow line, and the paper noted that not everyone supported it. ONWASA's report lists anticipated residential and commercial development among the flows the expanded Sneads Ferry plant is being built to take.
Water is in the plans too. At a March 19, 2026 work session, ONWASA staff described a Holly Ridge water tank and transmission main estimated at about $21 million: a $7 million elevated storage tank and about $14 million for a 24-inch main from Dixon to Folkestone Road. ONWASA has applied for an Economic Development Administration grant to cover part of it. The board took no formal action that day. At the same session, Chairman Royce Bennett raised the idea of coordinating the Holly Ridge-area force main with Greystone Road improvements to reduce road disturbance.
Commercial land is moving along US 17 as well. On September 15, 2026, the Planning Board recommended rezoning two vacant parcels on US 17 South, about 12 acres owned by the Ottaway family, from R-20 residential to commercial. The parcels sit across the highway from Sage's Ridge, and the board cited the town's Envision 2050 comprehensive plan. No one spoke against the request. The recommendation goes to Town Council.
What this means for a buyer
If you're comparing Holly Ridge with other coastal towns between now and 2029, the new-home choices sit at two ends. The builder pages show move-in-ready townhomes at Gateway Commons and finished homes at Summerhouse. Tar Landing is a new subdivision going ahead on septic with 36 first-phase lots, where the approved plan allowed a denser mix of townhomes and duplexes.
A buyer who wants a new compact home with low upkeep is looking at a short list in mid-November. A buyer who wants land will find Tar Landing's Phase 1 lots averaging close to a third of an acre, in a development whose concept plan allowed 5,000-square-foot lots.
FAQ
When does Holly Ridge get more sewer capacity? ONWASA's 2025 annual report puts completion of the 3.5-million-gallon-a-day Southeast Regional plant expansion in Sneads Ferry at late 2028 to early 2029. The Holly Ridge plant will close once its flow is sent there.
Is Tar Landing the same project as the annexation? No. Tar Landing is a roughly 98-acre planned unit development on Tar Landing Road, and its concept plan was approved in December 2024. The annexation the StarNews covered in February 2026 is a separate proposal that would double the town's size.
Where can I see current Holly Ridge homes alongside nearby beach towns? Our Holly Ridge neighborhood page and Wilmington and Carolina Beach page cover both sides of the county line.
If you own a home in Holly Ridge that's already on public sewer, buyers will be weighing it against Gateway Commons, Summerhouse and the new septic lots at Tar Landing. Before you list it, we'll show you how buyers are comparing it with new construction now. Talk with SERHANT. North Carolina and request your free home valuation and marketing plan.